Our O&M service helps prevent and solve electrical problems through testing, preventive maintenance, repair, replacement on either a routine or an emergency basis.
As far as Earthing system is concerned our activity will include the following:
Earth Electrodes
a) Measure soil resistivity at site by Wenner/Schlumberger Palmer method as detailed in IEEE 81 standard. This is essential to determine the resistance that can be expected from a healthy earth pit. The electrode resistance to earth shall be calculated as per formula given in clause no. 9.2.2 of IS3043 &Clause 9.5.3 of BS7430. (Incase of non availability of space within the plant, SR could be measured outside plant area to get representative values)
b) For measuring the resistance of individual isolated electrode for LT and other non-DG/Transformer create a temporary by pass arrangement for the earth pit to be tested by connecting its grounding electrode conductor to the nearest alternative earth pit.
Physical inspection of electrode for its condition to be done before carrying out testing. If damage found like broken neck /collar straightway the electrode shall be replaced with new one.
c) Isolate the earth pit under test and measure its resistance value by fall of potential method/Stakeless method and record the findings.